PV FARM 1.88 MW
UNIN-KOLONIA
01
A 1.88 MW photovoltaic farm was built in Unin-Kolonia, Garwolin County.
Over 3,000 state-of-the-art 620 W Jinko panels were installed across 2.2 hectares. The plant generates around 2,000 MWh of electricity annually — enough to power hundreds of households with clean energy.
This investment reduces CO₂ emissions by approximately 1,320 tonnes per year
and was completed in just 8 months, serving as an example of effective implementation of renewable energy projects.
[ ENERGY STORAGE ]
[ PHOTOVOLTAICS ]
[ RENEWABLE ENERGY ]
[ SOLAR FARM ]
- Installed capacity: 1.88 MW
- Location: Unin-Kolonia, Garwolin County, Masovian Voivodeship
- Land area: 2.2 ha
- Number of PV modules: 3,032 Jinko JKM620N-66HL4M-(V) panels, 620 W each
- Mounting system: Steel structure, south-facing layout, 2 modules vertically, Corab S.A.
- Inverters: 5 Sungrow SG350HX
- Transformer stations: STLmb 6×3 15/0.8, 2000 kVA, Elektromontaż Lublin
- Monitoring system: SCADA
- Average annual energy production: 2,000 MWh
- CO₂ emission reduction: approx. 1,320 tonnes per year
- Project completion time: 8 months